Project Completed
Budget
$800,000
Scope of Work
Conduct a detailed hydraulic evaluation of open channels, culverts, and bridges within the City using 2-D modeling. Installation of a Flood Early Warning System with up to 10 rain/stream gauges in each watershed.
Subdivisions, Areas, or Streets Impacted
Citywide

Project Status as of September 2021
This project was completed.
Original Schedule
The original schedule, as of September 2019, shows the Citywide 2D Model of Drainage System study in progress from quarter 4 of 2019 through quarter 3 of 2021.
Current Schedule
The current schedule, as of September 2021, shows the Citywide 2D Model of Drainage System study completed during quarter 4 of 2020 through quarter 2 of 2021. The flood gage stations are shown as complete from quarter 3 of 2020 through quarter 1 of 2021.