FM 518 and Wesley Drive Drainage Improvements

Budget

$3 million

Scope of Work

This project will focus improvements on capturing and conveying the stormwater runoff that exceeds the current storm sewer system capacity at the intersection of FM 518 and Wesley Drive. The improvements will include upsizing and installing a new storm sewer system to convey stormwater to Corum Ditch. The project will incorporate current drainage and stormwater design standards.

Subdivisions, Areas, or Streets Impacted

FM 518 and Wesley Drive 

map

project timeline-fm518 and wesley drive drainage-01

Project Status as of April 2023

The Texas General Land Office (GLO) approved the AUGF (Authority to use Grant Funds) on February 21st. Centerpoint gas lines in the TxDOT ROW that are in conflict need to be relocated. The LOSA (Local on System Agreement) has been submitted to TxDOT and is under review. 100% plan submittal is expected to be submitted for City interdepartmental review in April.  Dependent on TxDOT approving the LOSA, construction is anticipated to start in late Summer 2023..  

Original Schedule

The original schedule, as of September 2019, shows design programmed in quarter 4 of 2021 through quarter 2 of 2022 for FM518 & Wesley Dr. Drainage Improvements. Construction bidding is scheduled for quarter 3 of 2023 with construction following through quarter 4 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of December 2021, for the FM518 and Wesley Dr. Drainage Improvements project shows the grant application complete from quarter 1 of 2019 through quarter 2 of 2020. Grant award was complete in quarter 3 through 4 of 2020 with grant kickoff completed in quarter 1 of 2021. RFQ for design services required by the grant complete in quarter 2 of 2021. Design is programmed from quarter 3 of 2021 to quarter 2 of 2022. Construction bidding is programmed for quarter 3 of 2022. Construction is programmed for quarter 4 of 2022 through quarter 4 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Project Manager Contact Information

Jaime Dino
Phone: 281-554-1487
Email Jaime Dino