New Traffic Signals on League City Parkway

GO Bond Funding: $4.2 million New Traffic Signals on League City Parkway Project Sheet (PDF)

Scope of work: New traffic signals and turn lane improvements at Brittany Lakes Drive, Fennigan Lane, Landing Boulevard, Magnolia Lane, and West Bay Area Boulevard.

map

Traffic Signal - League City Parkway at Brittany Bay/Fennigan

Traffic Signal - League City Parkway at Brittany Bay/Fennigan

Project Status as of January 2022

Construction programmed in FY2022 in the FY2020-2024 CIP but advancing now to accelerate GO Bond program; Council awarded construction contract on December 8, 2020 for 240 calendar days from the notice to proceed; NTP issued on January 26, 2021; contractor mobilized during the week of February 22. Signal foundations poured, traffic poles and equipment have been ordered. Working on box culvert installation; scheduled through July at which time they will switch to paving work. Signal pole delivery/installation scheduled for early July. Construction was anticipated to be complete in October 2021, but due to a delay related to the electrical work for the signal, the project was substantially complete in January 2022.

Original Schedule

The original schedule, as of September 2019, shows the design phase of a New Traffic Signal at League City Parkway and Brittany Bay/Fennigan completed in quarter 3 of 2019. Construction bidding is scheduled for quarter 4 of 2021 with construction following through quarter 2 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of January 2022, shows the design phase of a New Traffic Signal at League City Parkway and Brittany Bay/Fennigan completed during quarter 4 of 2019. Construction bidding was complete in quarter 3 and 4 of 2020. Construction shows completion from quarter 1 through quarter 1 of 2022.

Traffic Signal - League City Parkway at Landing Blvd. 

Traffic Signal - League City Parkway at Landing Blvd.

Project Status as of December 2021

Council awarded design contract on April 14, 2020; 100% plans were received in April 2021 and finalized in late June 2021. Revised plans incorporating traffic control revisions and conduit for future fiber were resubmitted for review in October 2021, and plans are in final review. Right-of-way acquisition is currently in progress with anticipated completion in quarter 1 of 2022. Estimate bidding in quarter 1 of 2022.

Original Schedule

The original schedule, as of September 2019, shows the design phase of a New Traffic Signal at League City Parkway and Landing Boulevard beginning quarter 4 of 2019 through quarter 4 of 2020. Land acquisition is scheduled for quarter 3 of 2020 through quarter 3 of 2021.  Construction bidding is scheduled for quarter 4 of 2022 with construction following through quarter 1 of 2024.  Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of December 2021, shows the design phase of a New Traffic Signal at League City Parkway and Landing Boulevard completed from quarter 3 of 2020 through quarter 2 of 2021. Design begins again in quarter 4 of 2021 through quarter 1 of 2022 due to revisions incorporating traffic control and conduit for future fiber. Land acquisition is in progress for quarter 2 of 2021 through quarter 1 of 2022. Construction bidding is scheduled for quarter 1 of 2022 with construction following in quarter 2 of 2022 through quarter 1 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Traffic Signal - League City Parkway at Magnolia Meadow Ln.Traffic Signal - League City Parkway at Magnolia Meadow Ln

Project Status as of December 2021

Council awarded design contract on April 14, 2020; 100% plans were received in April 2021 and finalized in late June 2021. Revised plans incorporating traffic control revisions and conduit for future fiber were resubmitted for review in October 2021, and plans are in final review. Coordinating with CCISD to ensure adequate ingress/egress for Gilmore Elementary at the Magnolia Meadow Lane intersection. Right-of-way acquisition is currently in progress and anticipated to be complete in quarter 1 of 2022. Estimate bidding in quarter 1 of 2022.

Original Schedule

The original schedule, as of September 2019, shows the design phase of a New Traffic Signal at League City Parkway and Magnolia Meadows Lane beginning quarter 4 of 2019 through quarter 4 of 2020. Land acquisition is scheduled for quarter 3 of 2020 through quarter 3 of 2021. Construction bidding is scheduled for quarter 4 of 2022 with construction following through quarter 1 of 2024. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of December 2021, shows the design phase of a New Traffic Signal at League City Parkway and Magnolia Meadows Lane complete from quarter 3 of 2020 through quarter 2 of 2021. Design begins again in quarter 4 of 2021 through quarter 1 of 2022 due to revisions incorporating traffic control and conduit for future fiber. Land acquisition is in progress for quarter 2 of 2021 through quarter 1 of 2022. Construction bidding is scheduled for quarter 1 of 2022 with construction following from quarter 2 of 2022 through quarter 1 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Traffic Signal - League City Parkway at West Bay Area Blvd. 

Traffic Signal - League City Parkway at West Bay Area Blvd.

Project Status as of December 2021

Council awarded design contract on April 14, 2020; 100% plans were received in April 2021 and finalized in late June 2021. Revised plans incorporating traffic control revisions and conduit for future fiber were resubmitted for review in October 2021, and plans are in final review. Right-of-way acquisition is currently in progress and anticipated to be complete in quarter 1 of 2022. Estimate bidding in quarter 1 of 2022.

Original Schedule 

The original schedule, as of September 2019, shows the design phase of a new traffic signal at League City Parkway and West Bay Area Boulevard beginning in quarter 4 of 2019 through quarter 3 of 2021. Land acquisition is scheduled for quarter 3 of 2020 through quarter 3 of 2021. Construction bidding is scheduled for quarter 3 of 2023 with construction following through quarter 3 of 2024. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule 

The current schedule, as of December 2021, shows the design phase of a New Traffic Signal at League City Parkway and West Bay Area Boulevard complete from quarter 3 of 2020 through quarter 2 of 2021. Design begins again in quarter 4 of 2021 through quarter 1 of 2022 due to revisions incorporating traffic control and conduit for future fiber. Land acquisition is in progress from quarter 3 of 2021 through quarter 2 of 2022. Construction bidding is scheduled for quarter 1 of 2022 with construction following from quarter 2 of 2022 through quarter 1 of 2023. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Traffic Signal - Calder Rd. at FM517

Traffic Signal - Calder Rd. at FM 517

Project Status as of December 2021

GO Bond Project; programmed in CIP to begin design in FY2023 due to debt capacity and possibility of partnership with others.

Original Schedule

The original schedule, as of September 2019, shows the design phase of a New Traffic Signal at Calder Rd and FM517 beginning quarter 4 of 2022 through quarter 2 of 2023. Construction bidding is scheduled for quarter 3 of 2023 with construction following through quarter 3 of 2024. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.

Current Schedule

The current schedule, as of December 2021, shows the design phase of a New Traffic Signal at Calder Rd. and FM517 beginning in quarter 4 of 2022 through quarter 2 of 2023. Construction bidding is scheduled for quarter 3 of 2023 with construction following through quarter 3 of 2024. Construction time is an estimate as each bid is awarded based on cost and time submitted by the contractor.