Landing Blvd. Extension

Budget

$67,100 North Landing Extension Project Sheet (PDF)

Scope of Work

The proposed project is a new location roadway that would extend both Landing Boulevard and NASA 1 to intersect at a roundabout as a four-lane facility. The roadway would be divided by a raised median varying from 4 to 16 feet in width. The proposed design includes two 12-foot travel lanes in each direction, a 5-foot sidewalk constructed on one side of the roadway, and a 10-foot shared-use path on the other side. In addition, a 2,800-foot long bridge over Clear Creek and Newport Ditch (a tributary of Clear Creek), and a 100-foot long bridge over a narrow drainage channel are proposed. 

Subdivisions, Areas, or Streets Impacted

Clear Creek Village, Dem Shadows

map

project timeline-the landing drainage-01

Project Status as of July 2022

Following TxDOT’s approval of the proposed right-of-way mapping at the end of January 2022, City staff and consultants have been working on land acquisitions. TxDOT has requested from HGAC and League City to postpone the bid Letting to June 2023. The 100% plans and specifications were originally scheduled to be submitted earlier this week, however TxDOT has pushed the submittal back to coincide with their proposed new Letting date. The City is working with affected utilities for relocation of their facilities. The City is awaiting the Clear Creek crossing permit from the U.S. Army Corps of Engineers and the required wetland mitigation.

Original Schedule

The original schedule, as of September 2019, shows the design phase of North Landing Blvd Extension from quarter 1 of 2019 through quarter 3 of 2020. Land acquisition was scheduled to begin quarter 1 of 2020 through quarter 3 of 2020. Construction bidding is scheduled for quarter 4 of 2020 with construction following through quarter 2 of 2022. Construction will be bid and managed by TxDOT.

Current Schedule

The current schedule, as of December 2021, shows the preliminary design and environmental permit phase of North Landing Blvd. Extension complete in quarter 3 of 2019. Final design began in quarter 4 of 2019 and will progress through quarter 1 of 2022. Land acquisition began in quarter 1 of 2022 through quarter 4 of 2022. Construction bidding is scheduled for quarters 3 and 4 of 2022 with construction following in quarter 1 of 2023 through quarter 4 of 2024. Construction is planned through quarter 4 of 2024. Construction will be bid and managed by TxDOT.