Budget
$4.1 million
Scope of Work
The purpose of this project is to perform road base repairs, asphalt resurfacing, and/or full depth reconstruction as part of an annual infrastructure reinvestment program. This project includes a base bid of Seminole Drive, Glen Cove, and Mary Lane. Glen Cove has a bid alternate No.1A for using traditional construction methods and a bid alternate No.1B add/deduct for using the LithTec method. Other alternate add-ons include reconstruction of Cedar Avenue, Moody Avenue, and Tallow Forest.
Subdivisions, Areas, or Streets Impacted
Glen Cove Subdivision, Glen Cove Blvd., Seminole Drive, Mary Lane, Tallow Forrest, Moody Ave., and Cedar Ave
Project Status as of October 2022
Glen Cove: The contractor has installed the LithTec system on the southbound lane and is in the process of placing the first layer of level-up. Crews will then mill the northbound lane and prepare the base for the LithTec material. Once the base is stabilized with the LithTec material, they will place the first layer of level-up asphalt and then place the final layer of surface asphalt across both lanes. Crews will then place the shoulder dressing and clean up.
Mary Lane: Contractor has paused because due to some failing compaction numbers. Placing the first layer of asphalt was rushed and some areas will need to be redone. The City is meeting on site with the contactor, our design consultant, and our materials testing lab to evaluate the condition and make a plan moving forward.
Council has awarded the construction contract to Texas Materials Group, Inc. on May 24, 2022 with a Notice to Proceed issued on July 11, 2022. Construction is expected to be complete in January 2023.
Project Manager Contact Information
Scott Tuma
Phone: 281-554-1431
Email Scott Tuma