Phase 2 Reconstruction of Turner Street & Butler Road

Budget

$697,171

Scope of Work

The scope of this project is to reconstruct approximately 1,800 feet of existing two-lane asphalt roadway to a 24-foot-wide curb and gutter reinforced with concrete pavement along Turner Street from Hobbs to Butler Road. It also consists of reconstructing approximately 4,300 feet of two-lane asphalt roadway to a 24-foot-wide curb and gutter reinforced with concrete pavement on Butler Road from Turner Street to approximately 400 feet south of Sedona Drive.

Subdivisions, Areas, or Streets Impacted

Turner Street from Hobbs Road to Butler Road. Butler Road from Turner Street south to 400 feet south of Sedona Drive

Project Status as of May 2022

Project staff sent the City’s consultant comments pertaining to the 60% plans that were submitted previously in February. Project staff have also distributed design plans to all franchise utility companies that were identified to conflict with the proposed roadway improvements on March 28.  A utility conflict meeting will be set in the upcoming weeks to discuss a plan of action moving forward with the franchise utilities. Ninety percent plan submittals are expected to be submitted in early June 2022.  Construction is anticipated to start in October 2022.

Project Manager Contact Information

Jaime Dino
Phone: 281-554-1487
Email Jaime Dino