Budget
$221,121
Scope of Work
The scope of this project is to design an eastbound right turn lane from 450 linear feet west of Butler Road to 300 linear feet west of I-45 Southbound Frontage Road, and tie to TXDOT right turn lane. Approximately 2,200 linear feet of 12-foot-wide by 8-inch concrete pavement will be implemented to the design to improve mobility along League City Parkway thoroughfare.
Subdivisions, Areas, or Streets Impacted
League City Parkway (SH96) from Butler to 300 linear feet west of I-45 Southbound Frontage Road
Project Status as of July 2022
The consultant submitted the 90% plans and the easement exhibits for City review on June 21. Project Management
staff provided the latest set of drawings to all franchise utility owners and will be scheduling a meeting to discuss utility
relocation efforts for this project. The City anticipates completion of design, permitting, and easement acquisitions by
the end of 2022 and estimates construction in the second quarter of 2023.