Budget
$3,785,056
Scope of Work
This project consists of installing a 24-inch waterline down FM 646 from Dickinson Avenue to South Shore Boulevard, as well as up Tuscan Lakes Boulevard to FM 646. To date, four of the five segments have been installed. This final segment will be installed from FM 270 to South Shore Boulevard.
Subdivisions, Areas, or Streets Impacted
League City Parkway (SH96) from Butler to 300 linear feet west of I-45 Southbound Frontage Road
Project Status as of April 2023
This final phase of the Southeast Service Area Trunks project has wrapped up construction. This phase consisted of installing a 24-inch waterline down FM 646 from Dickinson Avenue to South Shore Boulevard, as well as up Tuscan Lakes Boulevard to SH 96. After a four (4) month construction delay due to a utility conflict, the contractor re-mobilized and completed construction in November 2022, including pressure testing. On December 19, 2022, the water main system was activated and placed into service by Public Works. Project close out is in it’s final stages.
Project Manager Contact Information
Jaime Dino
Phone: 281-554-1487
Email Jaime Dino