Budget
$361,080
Scope of Work
The purpose of this project is to systematically replace the City’s aging infrastructure. Staff has identified approximately 23,000 linear feet of waterline to be high priority for upgrades and replacement due to aged and deteriorated waterlines, undersized small diameter waterlines, ongoing maintenance issues, and updating pipe material.
Subdivisions, Areas, or Streets Impacted
Pecan Forest, Highland Terrace, and Clear Creek Heights subdivisions, and Boden and Bern Streets
Project Status as of May 2022
Project staff presented this design proposal for City Council consideration at the April 12 meeting. A notice to proceed was issued to the design consultant, ARKK on May 23. Design duration is scheduled for 365 days. Construction is slated for 2023.
Project Manager Contact Information
Jaime Dino
Phone: 281-554-1487
Email Jaime Dino